It took a lot of supports to keep pipes above battering water as they crossed Devore’s canyons. The kind of work being done for the water company in the 1940s is shown in the photo below by Harry H, Hall.

Devore Water Company Tidbits

History of Water Rates

Early cost of water was $1.50/month plus whatever ran over the weir.

Before 1949, the price of water was a flat rate of $3/month, but water was only available as pressure allowed. The assesment was $2.50/year, which often was not even collected. In 1949, metering started and rate schedules were issued.

In 1952, a total of somewhere around 673 shares were owned.

In 1961, 1000 cubic feet cost $1.17.
In 1968, 1000 cubic feet cost $4.00.
In 1977, 1000 cubic feet cost $6.00.
In 1979, 1000 cubic feet cost $7.25.
In 2000, 1000 cubic feet cost $8.50.

In 2007, over 485 water meters were in use.

The following rates are effective as of October 1, 2026 and were approved by the Board at the September 9, 2026 meeting.

Monthly Water Bill Charges (As of 10/1/2026)
Nitrate Project Loan Assessment Per Share $40.25 Board Approved 9/9/2026
Capital Improvement Project Assessment $17.75 Board Approved 9/9/2026
Monthly Standby Charge (by Meter Size)
5/8″ and 3/4″ $40.00
1″ $55.00
1 1/2″ $75.00
2″ $120.00
Over 2″ $150.00
Monthly Residential Usage Charge
(Basic Allotted Amount for Appurtenant Share Per Meter = 250 cubic feet water)
Per 100 cf Rates Board Approved 9/9/2026
250 to 2000 cf Per 100 cf $2.16
2001 to  4000 cf Per 100 cf $2.52
4001 to  6000 cf Per 100 cf $3.82
6001 to  8000 cf Per 100 cf $7.20
8001 to  10000 cf Per 100 cf $11.87
10001 to  20000 cf Per 100 cf $15.24
20001 to  40000 cf Per 100 cf $21.36
Over 40000 cf Per 100 cf $33.32
Monthly Commercial Usage Charge
(Basic Allotted Amount for Appurtenant Share Per Meter = 250 cubic feet water)
Per 100 cf Rates Board Approved 9/9/2026
250 to 2000 cf Per 100 cf $2.27
2001 to  4000 cf Per 100 cf $2.69
4001 to  6000 cf Per 100 cf $4.14
6001 to  8000 cf Per 100 cf $7.90
8001 to  10000 cf Per 100 cf $13.24
10001 to  20000 cf Per 100 cf $17.25
20001 to  40000 cf Per 100 cf $24.47
Over 40000 cf Per 100 cf $38.64
Allowance per Number of Owned Water Shares – Applies To All Residents
1 share =   250 cf of water at base rate
2 shares = 500 cf of water at base rate
3 shares = 750 cf of water at base rate
4 shares = 1000 cf of water at base rate
5 shares = 1250 cf of water at base rate
6 shares = 1500 cf of water at base rate
7 shares = 1750 cf of water at base rate
8 shares = 2000 cf water at base rate
9 shares = 2250 cf water at base rate
etc.
New Meter Fees
Meter Size Meter Price Notes
5/8″ Meter $6,500.00 Plus construction & capacity costs
3/4″ Meter $7,800.00 Plus construction & capacity costs
1″ Meter $9,750.00 Plus construction & capacity costs
1.5″ Meter $21,950.00 Plus construction & capacity costs
2″ Meter $45,000.00 Plus construction & capacity costs
Meters Larger than 2″ Board Approval
Capacity Charge Determined by size of meter
Installation Fee for Meters at construction cost $2,500.00 Minimum
Extra to cross asphalt street at construction cost $1,000.00 Minimum
Upgrading of new lines as required at construction cost
Office Fees
10 % APR Percent late fee on any balance over $50.00
Any charge over 30 days will be assessed a 1.5% late fee
Non Sufficient Fund Fees – Return Check $95.00 Per Share
Transfer Fee $95.00 Per Share
Name Changes Fee $50.00 Per Share
Replacement copy of lost certificate $50.00 Per Share
Photo copies for customers $0.30 Per Page
Rental Fees
Pedo Test – Fireflow Test $25.00
Rental Back Flow Device $25.00 Per Week
Rental Back Flow Device $3.50 per 100 cf usage
Refundable Deposit for hydrant & backflow device $2,500.00
State Loan Fee $8.83 Per Week